Archive for the 'Natural Resource Damages' Category

SUMMARY OF DEVELOPMENTS IN CERCLA AND NJ SPILL ACT: 2011

SteveK January 16th, 2012

This is a summary of some of the significant decisions of 2011 in CERCLA and N.J Spill Act litigation. ( Some of the decisions were previously reviewed in this blog.)

CERCLA

Arranger and Operator Liability:

In Nu-West Mining Inc. v. United States,786 F.Supp 2d 1082 (D.C. Idaho, 2011) the Federal District Court held that the U.S. Government was liable as both an arranger and operator under CERCLA at a site in the Caribou-Targhee National Forest that had been leased to a mining company. The court concluded that the permitting, inspection and oversight functions at four mines were sufficient involvement and control of the operations by the U.S. to impose liability.

The Court reviewed the law on arranger and operator liability.

A party is considered an arranger under CERCLA according to Burlington Northern & Santa Fe Railway Co. v. United States (BNSF), 129 S. Ct. 1870 (2009) when it “takes intentional steps to dispose of a hazardous substance.” Id. at 1879. Mere knowledge that spills would occur did not amount to “intent.” Further, the Court held that the analysis “requires a fact-intensive inquiry that looks beyond the parties’ characterization of the transaction as a ‘disposal’ or ‘sale’ and seeks to discern whether the arrangement was one Congress intended to fall within the scope of CERCLA’s strict-liability provisions.” Id.

For a party to be considered an operator of a facility under CERCLA  it must “manage, direct, or conduct operations specifically related to pollution, that is, operations having to do with the leakage or disposal of hazardous waste,  or decision about compliance with environmental regulations.” United States v. Bestfoods 524 U.S. 51, 66-67 (1998). If a party had the authority to control the cause of the contamination at the time of disposal, and actually exercised that control, then it is considered an operator. Id., citing, Kaiser Aluminum & Chem. Co. v. Catellus Dev. Corp., 976 F. 2d 1338, 1341 (9th Cir. 1992).

The Government began leasing mineral rights in the National Forest to various mining companies.  In accordance with the leases the Government inspected the mines to monitor the environmental conditions, properly disposing of mining waste, and to confirm royalty payments. The lease also required the lessees to “[prospect] diligently and to meet certain ore production requirements, and to pay a royalty fee.”  The Government also issued Special Use Permits so that rock waste dumps could be constructed on National Forest Lands adjacent to the leased lands. The Government also required the lessees to obtain “approval of plans for mining, waste disposal, and reclamation.”

The mine sites were determined to be contaminated with selenium, a naturally occurring chemical element that is found in a rock layer between phosphate ore zones. The mines were operated from 1960 until the 1990s. When the contamination was discovered in the 1990s, the lessee, Nu-West entered into Administrative Orders with the Government to remediate the sites. Nu-West claims to have spent over $10 million dollars and seeks to recoup those costs. In a motion for partial summary judgment Nu-West argued that the Government was an owner, arranger and operator under CERCLA. The motion did not address or resolve any defense to which the Government may be entitled, or any issue of damages.

The Court found that the Government not only owned the source of the contamination, it also had the authority to control the disposal of mining waste at the dump sites. The Court specifically noted that the lease provided that “no mining waste disposal could occur without its approval.” Further, the Court found that the Government exercised control over the disposal, and “showed its intent that disposal take place” by directing how the dumps should be covered.  The Court rejected the Government’s argument that it was acting in purely in a regulatory capacity, finding that its actions constituted a waiver of its sovereign immunity.” Citing, U.S. v. Shell Co. 294 F. 3d 1045, 1052-54 (9th Cir. 2002.); 42 U.S.C. §9620(a)(1) Accordingly, the Government was held as an arranger.

The Court also found there to be operator liability because the Government managed design and location of the dumps. In addition, the Government regularly inspected the dumps to ensure compliance with the mining plans and waste disposal guidelines.

In a subsequent motion reported at 2011 U.S. Dist. LEXIS 70854, the Court denied Nu-West’s motion for summary judgment on the Government’s counterclaim, seeking a ruling that the Government would not be entitled to legal fees. The Court was unable to conclude what costs may be “enforcement costs”  which a government may recover, as opposed to “necessary cost of response” which is what a private party may recover.

This case clarifies some of the issues on Governmental liability for actions at CERCLA sites, including that the Government can be liable when it is controlling the operations for its own benefit, not just in the use of its police power or in its sovereign capacity.

 

Owner Liability

In Los Angeles v. San Pedro Boat Works, 635 F. 3d 440 (9th Cir. 2011,) the Court held that the holder of a “revocable permit”  for a ship-berth in Los Angeles harbor had a mere possessory interest which did not arise to an ownership interest under CERCLA.

In this case, contamination arose from ship repairing activities that took place in Los Angeles Harbor. Pacific American purchased a revocable permit from the Harbor Commission in 1969 and held the permit for approximately 10 months. San Pedro Boat Works, a wholly owned subsidiary of Pacific American, was assigned the permit from Pacific American in 1970. San Pedro Boat Works was subsequently sold. Pacific American was acquired by BCI-Coca-Cola Bottling Company of Los Angeles in 1993.

Contamination was discovered in 1995 at the berth. The City cleaned up the contamination and commenced suit against San Pedro and Coca-Cola to recover the costs. San Pedro filed for bankruptcy shortly after suit was filed.

In deciding in favor of Coca-Cola, the Court first looked to CERCLA, but concluded that the definition of owner was tautological: an owner is “any person owning a facility.” 42 U.S.C. §9601(20)(A)(ii). The Court elected to rely upon the common law of the jurisdiction which distinguished title ownership from possessory interest.  It concluded that the “holder of a permit for a specific use of real property is not the owner of that real property.”  The Court, therefore, concluded that the permit holder was not the owner under CERCLA.  The Court rejected the test applied by the Second Circuit in Commander Oil Corp. v Barlo Equip, Co. 215 F. 3d 321 (2nd Cir. 2000) for de facto ownership: 1) whether the lease is for an extensive term and admits of no rights in the owner/lessor to determine how the property is used; 2) whether the lease cannot be terminated by the owner before it expires; 3) whether the leasee has the right to sublet all or some of the property without notifying the owner; 4) whether the lessee is responsible for payment of all taxes, assessments, insurance an operation and maintenance costs; and 5) whether the lessee is responsible for making all structural repairs. Id. at 330-331.

As a result there is a conflict as to what test is to be applied in the analysis of what constitutes an owner where the concepts of control over the operations and activities are at issue. The Ninth Circuit has focused on the common law, and has held this way both for the holder of an easement, see, Long Beach Unified School Distric v. Dorothy B. Godwin Cal. Living Trust, 32 F 2d 1364 (9th Cir. 1994), and now for a permit. Although the 2nd Circuit test was determined to create a “nebulous and flexible analytic framework” by the 9th Circuit, the Circuits are split on what test is to be applied.  It is unclear how the actual results would vary.

Arranger Liability

In Team Enterprises LLC v. Western Investment Real Estate Trust 2011 U.S.  App LEXIS 19881, the 9th Circuit concluded that the manufacturer of a dry cleaning machine was not liable for contribution to environmental cleanup costs under CERCLA.  Thea Plaintiff, a dry cleaner, used dry cleaning equipment manufactured by R.R. Street & Co. (Street) for their operations. The PCE-laden residue from the operations was deposited into a bucket for reuse; however, some was poured down the drain and leaked into the soil.

The Court analyzed whether a party can be considered an arranger under CERCLA where the equipment was sold for legitimate business purposes and was not created with the intent and purpose of disposing of hazardous waste. The Court took into account the requirement under BNSF that a party “must take intentional steps to dispose of a hazardous substance” to be considered an arranger. Supra, 129 S. Ct at 1879.

The Court also rejected the argument that Street had “exercised control over the disposal process” by designing the equipment that required the dry cleaner to dispose of the wastewater into the sewer.  The Court concluded that the instructions that suggested that the waste be poured into a bucket (which, according to the Plaintiffs, left no alternative but for the operator to pour that waste into the drain) did not present anything more than a suggestion or “recommendation;” there was no directive or other manner of control. Even the argument that Street knew that was how dry cleaners handled the residual waste was unavailing.  The Court affirmed the decision from the lower court that the facts do not support the requisite intent to dispose of waste as set forth by the Supreme Court in BNSF.

Arranger and Divisibility

The Lower Fox River cleanup litigation continues to provide interesting issues and analysis of a variety of issues under CERCLA.  There were a number of decisions in the case in 2011, the most significant one being Appleton Papers, Inc. et. al. v. George Whiting Paper Co., 776 F. Supp 2d 857 (E.D. Wis. 2011).

The Court had previously held that the Plaintiffs were not entitled to contribution for the expenses they had and will incur for cleanup costs “because they knowingly took that risk that the product that they mobilized [PCBs] would have long-lasting environmental consequences.” Id. at 859. Defendants sought to have the Court require that Appleton reimburse them for the costs they have incurred for their investigation and remediation at the site.  The Court conducted a thorough analysis and crafted a decision that placed most of the responsibility on the Plaintiff, except with regard to Operable Unit -1 (OU-1) which was upstream.

First, the Court addressed arguments that the Plaintiff should be liable as a successor to an arranger for the disposal of pollutants in OU-1. The predecessor, Appleton Coated Paper Company (ACPC) made carbon paper which utilized PCBs. ACPC sold waste from their processes through a broker that was used by other companies for making paper. The waste paper (known as “broke”) was recycled by the acquiring companies which resulted in PCBs being discharged into the Fox River Site.  Defendants argue that in this manner, ACPC arranged to dispose of a hazardous substance, thus making them liable for contamination at OU-1, even though their own discharges did not wind up in OU-1.  The Court conducted a thorough analysis of arranger liability under BNSF and concluded that although they did “enter into a transaction for the sole purpose of discarding a used and no longer useful hazardous substance;” however, there was insufficient evidence to support the conclusion that ACPC had the intent to dispose of the waste along with “the particular knowledge that non-trivial amounts of the broke waste product would inevitably end up in the river.” Id. at 864. The Court concluded that there were questions of fact, but indicated that it was unlikely that there would be sufficient evidence to support such a claim.

The Court also rejected that argument that all the operable units at the site were intertwined, and thus, Plaintiff could not obtain contribution from the Defendants (and therefore they were entitled to reimbursement) for costs for OU-1. The Court, however, confirmed a prior ruling that the costs for OU-2 through 5 fall squarely and completely on the Plaintiffs on the basis of fault, and that fault was such an overriding factor that is outweighed by any basis to impose equitable shares on the Defendants.  The Court then went on the wrestle with particular costs, including deciding that the costs that have been incurred were not outside the statutory limitations periods.

Subsequent Work Causing Release

In Saline River Properties LLC v. Johnson Controls, 2011 U.S. Dist. LEXIS 119516 the U.S. District Court for the Eastern District of Michigan, addressed whether a developer could be liable under CERCLA for conducting  development activities that may have moved contamination on the site and required additional cleanup.  Johnson Controls had owned property that it was remediating under a state issued administrative order.  Plaintiff became the operator of the property and at some point destroyed the building slab which Johnson alleges resulted in the migration of contaminants that would not have otherwise occurred.  The Court concluded that although passive migration would not have resulted in liability, there were questions of fact as to whether this action caused a release.

Citizens’ Suits

In Pakootas v. Teck Cominco (Pakootas II), 2011 U.S. App. LEXIS 10931 the 9th Circuit ruled that environmental groups, Indian tribes and other non-EPA parties may not bring a citizens’ suit to enforce the penalty provisions of CERCLA.

Pakootas II is part of the continuing dispute concerning the pollution of the Columbia River. The pollution originated from mining operations in British Columbia. Teck Cominco Metals, a Canadian mining company operated a smelter north of the U.S. –Canadian border which generated and disposed of slag into the Columbia River. Negotiations between the EPA and Teck Cominco American, Inc. faltered on issues of Canadian sovereignty and jurisdiction. The EPA eventually issued a unilateral administrative order (Order) directing Teck to investigate the nature and extent of contamination in the Upper Columbia River basin, and to evaluate remedial options.  Teck did not comply and the EPA took no enforcement actions, nor did it seek penalties.

Plaintiffs, later joined by the Confederated Tribes of the Colville Reservation and the State of Washington, pursued a citizens’ suit seeking:  (1) a declaration that Teck had violated the Order; (2) injunctive relief compelling Teck to comply with the Order; (3) penalties for non-compliance with the Order;  and(4) attorney fees and costs.

After Teck’s motion to dismiss the case based upon the argument that EPA could not apply CERCLA extra-territorially was denied, Teck and the EPA entered into a “contractual agreement” to address the contamination at the site.  As part of the agreement, the EPA agreed to a covenant not to sue Teck for penalties or injunctive relief relating to non-compliance with the Order, subject to its satisfactory performance of its obligations under the agreement.

Plaintiffs amended their complaint and dismissed the claims for injunctive and declaratory relief, but continued to assert the claims for penalties for non-compliance with the Order. The 9th Circuit affirmed the dismissal of the suit concluding that the penalty provisions are a “hammer” to be wielded exclusively by the EPA to compel compliance. Further, the Court aptly noted that if Teck were compelled to pay the penalties to Plaintiffs prior to the agreed upon remediation,” it might find it economically advantageous to walk away from the further cleanup efforts…” which would have a perverse result, and would not further the intent to compel site remediation.

 

Section 113 & Private Nuisance Claims

On August 13, 2011, the Federal District Court for the District of New Jersey continued to clarify the limits of Section 113 claims under CERCLA and  also addressed common law claims of a subsequent property owner in Queens West Development Corporation v. Honeywell International, Inc. 2011 U.S. Dist. LEXIS 91795. Plaintiff acquired property formerly operated by Warren Chemical Works, which was subsequently acquired by Honeywell. The property was contaminated from discharges of substantial amounts of creosote, coal tar, and related substances. The property was to be redeveloped by plaintiff for residential, commercial and recreational uses. Plaintiff claimed to have incurred over $16 million in investigation and remediation costs, and anticipated total response costs that would be equal to or exceed $20 million. Defendant moved for dismissal of various counts of the complaint including claims in Count Two of the Complaint, under Section 113 of CERCLA, claims in Count Three for common law private nuisance, and claims in Count Four for restitution.  In deciding the case, the Court addressed the intersection between claims under Section 107 of CERCLA and Section 113. The Court noted that the case presented a unique issue: “whether a party that voluntarily undertakes a cleanup action can maintain a claim for contribution under § 113(f)(3)(B), when it has simultaneously asserted a claim for cost recovery under § 107(a).” The Court noted that courts have explained that Section 107 “authorizes the United States, a state, or `any other person’ to seek reimbursement for all removal or remedial costs associated with the hazardous materials on the property, provided that those actions are consistent with the National Contingency Plan,” and that the United States Supreme Court held in Atlantic Research that the “plain language” of § 107 “authorizes cost-recovery action by any private party, including PRPs.” As a result, a private party is not required to establish its own liability in order to assert a claim under  Section 107. Section 113(f)(3)(B), however, allows the assertion of a right of contribution only “to PRPs that have settled their CERCLA liability with a [S]tate or the United States through either an administrative or judicially approved settlement.” Since Plaintiff had voluntarily incurred the response costs, is not a PRP, and did not enter into an approved settlement or resolved all their liability to the U.S. or the State of New York, they could not maintain the  Section 113 claim. Thus, the Court dismissed the  Section 113 claim contained in the Second Count.

The Court next addressed the claims for private nuisance. As the proceeding was in New Jersey, but involved New York property, the Court considered the law of private nuisance in both jurisdictions. The Court concluded that the law was the same, and that although a private nuisance “consists of an interference with one’s interest in the private use and enjoyment of land” it only applies to interference with use of adjoining land, not to subsequent owners of the same property.

Finally, the Court refused to dismiss the restitution claim. Defendants argued that it should be dismissed since it is preempted by CERCLA. The Court refused to dismiss the claim, however, since it remained an alternative common law claim that would survive if the Plaintiff fails to prove the claim under Section 107 of CERCLA.

Case to Watch: Sackett

Sackett v. EPA is a case that is scheduled for argument before the U.S. Supreme Court this term. Although it is not a CERCLA case, it may have a significant impact on enforcement of federal environmental statutes.  The primary issue presented by Sackett is whether pre-enforcement review is available for EPA administrative orders. Pre-enforcement review refers to the ability of the recipient of such an order to obtain judicial review of the order without having to wait to be sued by the EPA. This is not applicable to CERCLA since CERCLA has an express provision prohibiting pre-enforcement review. 42 U.S.C. §9613(h).

The Court will consider whether a bar to pre-enforcement review can be implied into the Clean Water Act (CWA), as has been argued by the EPA, and whether such an implied ban would violate the due process clause of the U.S. Constitution.

In Sackett the plaintiffs had filled a wetland area on their 0.63 acre parcel without a CWA permit. The EPA issued an administrative compliance order requiring that the fill be removed and that the wetland be restored.  The Sacketts petitioned the EPA for a hearing to challenge the wetland determination. After the EPA refused, the Sacketts filed suit.  The District Court dismissed the suit and the Sacketts appealed to the 9th Circuit.  Before the 9th Circuit they argued (1) that the Administrative Procedures Act (APA) allows pre-enforcement review of CWA compliance orders; and (2) that pre-enforcement review is required by due process.

The Circuit Court rejected both arguments. It rejected the argument under the APA essentially finding that pre-enforcement review is not provided for in the CWA and that the presumption in favor of judicial review is overcome where “congressional intent to preclude judicial review is fairly discernible in the statutory scheme.” Sackett v. EPA 622 F. 3d 1139,1143 (9th Cir, 2010). The Court concluded that pre-enforcement review would frustrate the goal of addressing environmental problems quickly and would negate the EPA’s statutorily created choice between filing a suit or acting unilaterally through an administrative order.

The 9th Circuit rejected the due process arguments finding that it had been satisfied because: (1) judicial review was available once the EPA brings an enforcement action; (2) the Sacketts could have sought to obtain a §404 permit to fill the property, which would be reviewable by the district court if denied; and (3) the court, not the EPA, can impose penalties under the CWA based upon a range of factors. [1] The decision could have far reaching implications, even effecting CERCLA if the Supreme Court reverses on the basis of due process. [2]

 

NEW JERSEY SPILL ACT

Primary Jurisdiction

In Magic Petroleum, Inc. v. Exxon Mobil, 2011 N.J. Super. Unpub. LEXIS 2021, the New Jersey Appellate Division dismissed, without prejudice, Magic’s claim for contribution of remedial costs against Exxon due to NJDEP’s primary jurisdiction of the remedial investigation at the plaintiff’s property. Plaintiff had been the subject of an administrative consent order (ACO) to investigate and remediate contamination at its property resulting from leaking underground storage tanks.  Plaintiff contended that the majority of the contamination came from the neighboring Exxon station and refused to comply with its obligations under the ACO until the NJDEP required Exxon to participate in the investigation. Magic litigated its obligations under the ACO through administrative proceedings, and was required to follow the order. Magic, however,  continued to refuse to conduct the investigation, insisting that the investigation should be imposed upon and shared by Exxon. The NJDEP eventually took over the investigation of the plaintiff’s property. Magic then commenced a contribution action against Exxon.

Exxon filed a motion to stay or dismiss the proceedings, without prejudice, pending the NJDEP’s investigation and remediation of the Magic property, arguing that the NJDEP’s efforts must precede any decision by the court. The trial judge dismissed the case, deferring to the NJDEP’s primary jurisdiction. The Appellate Division affirmed.  The Appellate Court noted that under the doctrine of “primary jurisdiction” a court may defer to an agency where the resolution of an issue is within the special competence of the agency. The court further noted that private contribution rights under the Spill Act require the court to allocate responsibility for remediation costs, but that the initial determination of whether a party is responsible can be decided by the NJDEP, and that “only the DEP can define the contaminants, determine the extent of the discharge, identify the authorized forms of investigative testing, and permissive methodology of cleanup.” Furthermore, “to be entitled to reimbursement and contribution under the Spill Act, a party must obtain written approval under from the DEP of the investigation and proposed remedial action.”  Accordingly, the court concluded that these decisions were within the scope of the special expertise of the DEP and should be determined prior to the case being able to proceed.

This decision demonstrates that a responsible party under the Spill Act that does not conduct investigation and remediation, but allows it to be done by the State, does so at its peril. To do so may have a significant impact in the party’s ability to pursue a contribution claim against other responsible parties, as it allows the NJDEP to determine and define the scope of the investigation, remediation, and possibly to potentially influence any future contribution claim or allocation. It is interesting to consider the effect of the Site Remediation Reform Act (SRRA) on the statements by the court that the DEP will define the contaminants, the extent of the discharge, the forms of investigation and the method of cleanup. Under the SRRA these determinations can be made by a Licensed Site Remediation Professional (LSRP), in accordance with the regulations for site investigation and remediation, referred to the Tech. Regs.  Accordingly, it may not be that the DEP has to make these decisions. This points, again, to the importance of the party seeking contribution to address and control the response in order to be able to develop the information, and assert and control the contribution claim.

Nexus

In NJDEP v. Ofra Dimant, et.al 418 N.J. Super 530 (App. Div. 2011), cert. granted, 208 N.J. 381 (2011), the New Jersey Appellate Division recently confirmed that liability under the Spill Act, requires a connection between the discharge of a contaminant and the contamination of the environment of that contaminant that was caused by the discharge. In that case, the defendants included succession of owners and operators of a dry cleaning establishment. The contamination in the groundwater included the well-known dry cleaning chemical, PCE, as well as the byproducts of its degradation: TCE and DCE.  There was evidence that the PCE was related to the dry cleaning operations. All but one of the direct defendants settled with the State.  The remaining defendant went to trial. The trial judge found that although there were discharges or releases of PCE during the stewardship of the remaining defendant, there was no proof that those discharges went through the asphalt and contaminated the environment.  Since there was no nexus between the discharge and the remediation, the claims against the defendant were dismissed. The State also sought leave to amend the complaint to add certain other prior operators. The denial of that motion by the trial judge was affirmed as being made too late in the case; in fact, it was made near the end of the trial.  This case affirms the need for the State or any plaintiff in a Spill Act case to demonstrate a nexus; and further reaffirms that there is no liability for passive migration of contaminants during the ownership of property.

NRD Common Law Claims – Limitations of Actions

In New Jersey Dep’t of Env. Protection v. Exxon Mobil Corp, 405 N.J. Super 395 (App. Div. 2011) the court held that the State’s common law strict liability claims for NRDs were not barred by the general ten-year statute of limitations applicable to actions commenced by the State. N.J.S.A. 2A:14-1.2. The court, reversing the trial court, held that an exception to the ten-year statute, specific to environmental laws, known as the Extension Statute, N.J.S.A. 58:10B-17.1, applies not only to statutory environmental laws, but also to common law causes of action implementing environmental programs.
The Extension Statute provides:

b. (1) Except where a limitations provision expressly and specifically applies to actions commenced by the State or where a longer limitations period would otherwise apply, and subject to any statutory provisions or common law rules extending limitations periods, any civil action concerning the payment of compensation for damage to, or loss of, natural resources due to the discharge of a hazardous substance, commenced by the State pursuant to the State’s environmental laws, shall be commenced within five years and six months next after the cause of action shall have accrued.

Exxon argued that the Extension Statute’s use of the term “environmental laws” after a listing of 9 prior statutes,  limited the extension to statutory causes of action. The Appellate Division, however, looked to legislative history and concluded that the legislature intended to expand the scope of the authority of the DEP, not to limit it. As a result, NJDEP has the ability to pursue common law causes of action, along with the strict liability provision of Spill Act, in matters involving NRDs; neither of which will be constrained by the general ten-year statute. This decision may be important as common law remedies and damages may be broader and may permit the State to seek to present their case before a jury as there is some question whether there is a right to a jury trial under the Spill Act.

 

In a separate decision, the Appellate Court also ruled on the State’s claim for an interlocutory payment by Exxon Mobil for natural resource damage assessment costs of approximately $1 million.  The costs represent the invoices of five experts that prepared reports for DEP regarding the claimed natural resource damages under the Spill Act. The Court affirmed the trial court’s denial of the interim payment since there is a significant dispute as to the reasonableness of the costs and whether they are duplicative of defendant’s efforts. The panel concluded that the award of such costs is best reserved until resolution of the factual issues at trial.

NRD : Use of Resource Equivalency Analsyis (REA)

In  NJDEP v. Union Carbide, (Middlesex County, MID-L-5632-07, March 29, 2011) the trial Court rejected for the second time the State’s effort to employ a resource equivalency analysis (REA) or habitat equivalency analysis (HEA) to place a value on the loss of use of groundwater as a natural resource. The trial court had previously rejected REA in NJDEP v. Essex Chemical, (Middlesex County, Docket No.: MID-L-5685-07, July, 2010). The trial court concluded that the expert had not conducted a proper analysis of the particular services that were claimed to have been lost by the public due to the contamination, other than the remedial costs which were being conducted by the defendant. The court also ruled that there was no basis to compel the defendants to cleanup more expeditiously since the entire remedial endeavor had been with the approval and oversight of the NDJEP, albeit a different arm than the Office of Natural Resources and Recovery (ONRR). Finally, the court rejected the State’s nuisance claim since the plaintiff’s had not satisfied their burden of showing that the contamination of the groundwater interfered with the public’s use or enjoyment of the resource, further noting that the groundwater in question was never available to the public since it was below private property; therefore. “Plaintiffs have not shown how the public has been deprived of anything.” [Slip. Op. p. 13]


[1] Similar issues were addressed by the N.J. Supreme Court in In the Matter of the Directive to Kimber Peteroleum, 110 N.J. 69 (1988)

[2] It may be questionable whether the Court would go so far, considering it refused to consider a similar challenge regarding CERCLA administrative orders in General Electric v. Jackson, 595 F. Supp. 2d 8 (D.D.C. 2009).

DiFrancesco, Bateman, Coley, Yospin, Kunzman, Davis, Lehrer & Flaum, PC (www.dbnjlaw.com ) is a full service law firm in New Jersey which provides a broad range of legal services, including the representation of clients in environmental and defense of toxic exposure matters. For additional information about the matters in this bulletin or in the firm’s environmental practice, please contactSteven A. Kunzman, Esq. who heads our Environmental and Latent Injury Litigation Department.

The information contained in this blog is intended solely for informational purposes; it is a advertising publication of DiFrancesco, Bateman, Coley, Yospin, Kunzman, Davis, Lehrer & Flaum P.C.This publication is intended to alert recipients of developments in the law and is not intended to provide legal counsel, advice or opinion on any specific facts or circumstances. The contents are intended as general information only. You are urged to consult a member of this firm or your own attorney concerning your particular situation and any specific legal questions you might have.


Steven Kunzman to Co-Chair Seminar on Groundwater Contamination

SteveK August 15th, 2011

Steve Kunzman, partner in the firm, will be a co-chair of a comprehensive conference:

Groundwater Contamination and Vapor Intrusion Cases

The seminar, which will be put on by Law Seminars International, will take place at the Sheraton Newark Airport Hotel on September 15 and 16.

For more information and to register go to: http://www.lawseminars.com/seminars/11GWATNJ.php

The speakers include noted attorneys, remediation consultants and and other noted experts in the field. The seminar is co-chaired by Ira Gottlieb of McCarter & English. Steven and Ira will also be speaking on insurance coverage issues relating to groundwater claims.

The N.J. App. Div. rules that common law causes of action for NRD are subject to extended statute of limitations for environmental cleanup, and in a separate decision, that NRD assessment cost reimbursement must await the end of the case.

SteveK June 1st, 2011

As a follow up to the recent post on the trial court in NJDEP v. Saint-Gobain, the New Jersey Appellate Division has taken a contrary view, which now governs the issue in New Jersey. In a published opinion in the ongoing litigation regarding Exxon Mobil’s Bayway and Bayonne facilities, New Jersey Dep’t of Env. Protection v. Exxon Mobil Corp, the court held that the State’s common law strict liability claims for NRDs were not barred by the general ten-year statute of limitations applicable to actions commenced by the State. N.J.S.A. 2A:14-1.2. The court, reversing the trial court, held that an exception to the ten-year statute, specific to environmental laws, known as the Extension Statute, N.J.S.A. 58:10B-17.1, applies not only to statutory environmental laws, but also to common law causes of action implementing environmental programs
The Extension Statute provides:
b. (1) Except where a limitations provision expressly and specifically applies to actions commenced by the State or where a longer limitations period would otherwise apply, and subject to any statutory provisions or common law rules extending limitations periods, any civil action concerning the payment of compensation for damage to, or loss of, natural resources due to the discharge of a hazardous substance, commenced by the State pursuant to the State’s environmental laws, shall be commenced within five years and six months next after the cause of action shall have accrued.
Exxon argued in that the Extension Statute’s use of the term “environmental laws” after a listing of 9 prior statutes limited the extension to statutory causes of action. The App. Div, however, looked to legislative history and concluded that the legislature intended to expand the scope of the authority of the DEP, not to limit it. As a result, NJDEP has the ability to pursue common law causes of action, along with the strict liability provision of Spill Act, in matters involving NRDs; neither of which will be constrained by the general ten-year statute. This decision maybe important as common law remedies and damages may be broader and may permit the State to seek to present their case before a jury as there is some question whether there is a right to a jury trial under the Spill Act.

 

In a separate decision the Appellate Court also ruled on the State’s claim for an interlocutory payment by Exxon Mobil for natural resource damage assessment costs of approximately $1 million.  The costs represent the invoices of five experts that prepared reports for DEP regarding the claimed natural resource damages under the Spill Act. The Court affirmed the trial court’s denial of the interim payment since there is a significant dispute as to the reasonableness of the costs and whether they are duplicative of defendant’s efforts. The panel concluded that the award of such costs is best reserved until resolution of the factual issues at trial.

DiFrancesco, Bateman, Coley, Yospin, Kunzman, Davis & Lehrer, PC (www.dbnjlaw.com ) is a full service law firm in New Jersey which provides a broad range of legal services, including the representation of clients in environmental and defense of toxic exposure matters. For additional information about the matters in this bulletin or in the firm’s environmental practice, please contactSteven A. Kunzman, Esq. who heads our Environmental and Latent Injury Litigation Department

 

In NRD claim, trial Court dismisses common law causes of action of nuisance and trespass under the statute of limitations as they are not “environmental laws” and there was no “continuing tort.”

SteveK May 20th, 2011

In NJDEP v. Saint Gobain Plastics Corp. DiFrancesco, Bateman succeeded in having the State’s common law claims for natural resource damages (NRD) dismissed under New Jersey’s 10 year statute of limitations for the State’s assertion of claims: N.J.S.A. 2A:14A-1.2.  Contamination was discovered at defendant’s property in 1991. The defendant entered into an Administrative Consent Order and commenced site remediation immediately. The remedial efforts have continued to date.  The State was aware of the discharge in 1991, but did not institute a claim for NRD until 2005. Although defendant was previously held liable under the New Jersey Spill Act, the defendants sought summary judgment on the State’s common law claims for nuisance and trespass.  Judge LaConte of the Superior Court of Passaic County ruled in favor of defendant, holding that the common law claims for NRD do not constitute claims under the “State’s environmental laws” as defined in N.J.S.A.  58:10B-17.1.c., and therefore, the limitations period would not be extended for 5 years and 6 months from January 1, 2002 as provided for in section N.J.S.A.  58:10B-17.1.b. The Court concluded that since the statute extending the time for filing referred to nine specific statutes, and then referred to ,”… any other law or regulation by which the State may compel a person to perform remediation activities on contaminated property…” that the prior language demonstrated the intent of the legislature to limit the extended time period to statutes, not common law causes of action that may be used for purposes other than environmental protection.

Judge LaConte also rejected the State’s alternative theory that the continued presence and alleged migration of contaminants in the ground water constituted a continuing tort. The Court concluded that the “curative action” occurred when the seepage pit was removed in1991 and, as a result, no “new” contamination occurred. As a result, Judge LaConte ruled that “[a]lthough the effects of the discharge are still present…and may persist for decades, the alleged nuisance and trespass caused by the defendants no longer continued after 1991.” The Judge observed that if the tort was deemed to continue until the “end of remediation, long after the cause of the contamination had been removed, it would provide plaintiffs with an almost infinite amount of time to file common law causes of action.” In fact, he noted, this would even provide the State more time to file common law claims than had been extended by the legislature in N.J.S.A. 58:10B-17.1.

The decision is presently unreported. A copy can be obtained from Steven A. Kunzman, who represents Saint-Gobain in the matter.

DiFrancesco, Bateman, Coley, Yospin, Kunzman, Davis & Lehrer, PC (www.dbnjlaw.com ) is a full service law firm in New Jersey which provides a broad range of legal services, including the representation of clients in environmental and defense of toxic exposure matters. For additional information about the matters in this bulletin or in the firm’s environmental practice, please contactSteven A. Kunzman, Esq. who heads our Environmental and Latent Injury Litigation Department

 

 

NJ District Court rules that NJDEP waived its NRD claims

SteveK October 5th, 2010

On September 29, 2010, in FMC v. American Cyanamid consolidated with U.S. v FMC Corporation, Judge Cavanaugh of the U.S. District Court for New Jersey granted summary judgment to FMC Corporation  ruling that the NJDEP had waived its right to assert claims for natural resource damages (NRD) for a Superfund site in Franklin Township, N.J.  The parties agreed that in 2001 a coordinator for the NJDEP Office of Natural Resource Recovery (ONRR) prepared a written internal memorandum in which it was stated that the NJDEP would not assess NRD for the site because the groundwater plume did not extend off-site and because the proposal was being reviewed to re-inject treated water into the ground.  The position was conveyed orally to counsel for FMC. This position was consistent with the NJDEP’s policy for recovery of NRD which had been implemented in the 1990s. The policy was subsequently changed in 2002 and the change was memorialized in Policy Directive 2003-07 which provided that the ONRR would employ a settlement formula to evaluate and assess NRD, including for on-site groundwater. The position that there would be no claim for NRD for the FMC site; however, was subsequently confirmed during the course of settlement discussions in a letter from the office of the Attorney General in 2003.  Judge Cavanaugh concluded that the letter to FMC from the ONRR in 2003 (along with the prior statement in 2001) constituted a knowing and intentional waiver of any claims for NRD for the groundwater at the site. The court rejected the government’s argument that it can change its policies for the benefit of the public without creating rights in parties who claim to have relied on an old policy.  The court agreed that the government can change its policies, but concluded that it cannot expressly waive its rights two times in the span of two years “and then about face years later.” The judge concluded that allowing such a result “would serve to completely alter the calculus of the litigation and undermine settlement negotiations that the parties engage in with the State.” The claims of New Jersey for NRD were, therefore, dismissed.

This case demonstrates that New Jersey’s policies on NRD are continually developing. It is unlikely that a memorandum stating that the NJDEP will not be seeking NRD will be available in most cases. This decision does, however, indicate that the effort to obtain NRD for groundwater that is not likely to go off site is, at its core, a decision based on policy, not necessarily science.

DiFrancesco, Bateman, Coley, Yospin, Kunzman, Davis & Lehrer, PC (www.dbnjlaw.com ) is a full service law firm in New Jersey which provides a broad range of legal services, including the representation of clients in environmental and defense of toxic exposure matters. For additional information about the matters in this bulletin or in the firm’s environmental practice, please contactSteven A. Kunzman, Esq. who heads our Environmental and Latent Injury Litigation Department

NJ Trial Court Rules against NJDEP on NRD claim for failure to prove compensable harm or loss.

SteveK August 17th, 2010

In NJDEP v. Essex Chemical Corporation, a trial court of the New Jersey Superior Court recently ruled that the NJDEP had failed to prove that contamination to ground water resulted in compensable harm or loss entitling the State to an award of natural resource damages (NRD.)  Essex Chemical had owned and operated a facility where chlorinated volatile organic compounds were handled and later found in ground water. Essex commenced remedial actions under New Jersey law in 1984 and has continued to meet their obligations to conduct site remediation to the present day.

The NJDEP commenced an action for NRD in 2007, contending that the contamination to the ground water has resulted in a compensable loss to the people of the State and entitles the State to damages under the NJ Spill Act. The evidence at trial demonstrated that the remedial work was approved by the NJDEP and complied with the regulations governing site remediation (Tech. Regs.). The State’s expert on resource economics utilized a resource equivalency approach (REA) to support his damage evaluation, positing that the value of the loss can be based upon the cost of land that would support the same recharge to the ground water of the area contaminated. The Court rejected the expert’s opinion holding that it was not convinced that the method of calculation of compensatory damages was proper for the resource in question. The Court acknowledged that the REA approach was appropriate for loss of wildlife (e.g. fish, birds), or where the contamination has an effect on human health. Where, however, no such harm was identified, the Court did not accept the expert’s method of assigning values “to things that are normally invaluable,” presented as “non-use” values.  Since there was no evidence that the land in question will be developed nor any evidence that there was an intention to use the ground water or what it’s “non-use” value would be, the court found in favor of Essex Chemical and dismissed the claims.

DiFrancesco, Bateman, Coley, Yospin, Kunzman, Davis & Lehrer, PC (www.dbnjlaw.com ) is a full service law firm in New Jersey which provides a broad range of legal services, including the representation of clients in environmental and defense of toxic exposure matters. For additional information about the matters in this bulletin or in the firm’s environmental practice, please contactSteven A. Kunzman, Esq. who heads our Environmental and Latent Injury Litigation Department.

Remaining defendant is liable for past costs not covered by CERCLA consent decree.

SteveK August 17th, 2010

In U.S. v. Iron Mountain Mines, the U.S. District Court for the Eastern District of California granted summary judgment to the plaintiffs against Iron Mountain Mines and T.W. Arman for past costs which had not been resolved in a consent decree in which claims against other PRPs at the Iron Mountain Mines Superfund Site were settled.  The plaintiffs had previously settled with the other PRPs for approximately $154 million of insurance to cover future cleanup costs over 30 years, $10 million for natural resource damages, and an additional $7 million for future clean up not covered by the insurance. The defendants argued that the settlement amounts well exceeded the $26 million in past costs that had been incurred prior to February 29, 1996 which were being sought from them, therefore providing plaintiffs complete recovery.  Defendants argued, further, that it would not be known until after the 30 year period for payment of cleanup under the insurance policy whether the plaintiffs would not be made whole. The plaintiffs argued that no money had been received for the past costs.  The Court agreed with the plaintiffs, finding that the consent decree did not address past costs, but only future remedial costs and NRD. Since Section 113(f)(3) of CERCLA permits suit against non-settling responsible parties if the relief obtained in a settlement was not complete, the Court held for the plaintiffs.

This decision points to the essential need for a party to be informed in every step in the negotiation of a settlement, particularly if they are not a party to the settlement. As in the recent decisions of the 9t Circuit,  U.S. v Aerojet, and the 10th Circuit, U.S. v Albert Investment Co., it s important to take an active position, and where appropriate move to intervene,  on a motion or action to approve a CERCLA consent decree. Indeed, it has been acknowledged that CERCLA can impose harsh results on non-settling PRPs. See, United States v. Davis, 261 F. 3d. 1, 28 (1st Cir. 2001).

DiFrancesco, Bateman, Coley, Yospin, Kunzman, Davis & Lehrer, PC (www.dbnjlaw.com ) is a full service law firm in New Jersey which provides a broad range of legal services, including the representation of clients in environmental and defense of toxic exposure matters. For additional information about the matters in this bulletin or in the firm’s environmental practice, please contactSteven A. Kunzman, Esq. who heads our Environmental and Latent Injury Litigation Department.

9th Circuits holds owner of property at time cleanup costs are incurred is the owner under CERCLA

SteveK August 17th, 2010

On July 22, 2010, in State of California v. Hearthside Residential Corp., the court addressed a question of first impression: “whether the ‘owner and operator status under [CERCLA] is determined at the time that cleanup costs are incurred or instead the time that a recovery lawsuit seeking reimbursement is filed.” The concluded that the owner is determined at the time cleanup costs are incurred.

Hearthside had purchased property known as Fieldstone Property in Huntington Beach, California with the knowledge that it was contaminated with PCBs. Hearthstone entered into a consent order with the State in which it agreed to remediate the property, then sold to the property to the California State Lands Commission. The State determined that the adjacent residential site was also contaminated with PCBs which it alleged had migrated from the Fieldstone Property. The State considered Hearthstone responsible; however, Hearthstone disagreed, contending that it was not the owner when the suit was filed. The State, therefore, contracted to remediate the property and subsequently filed a complaint against Hearthstone.

Since CERCLA does not provide a clear answer to the issue of when a party is considered an owner for purposes of liability, and no case dealt with the issue directly, the court considered other aspects of the statute. The court concluded that the issue best aligns with CERCLA’s statute of limitations. Since the limitations provisions are triggered either (1) at the completion of a removal action, or (2) at the initiation of the remedial action, the court concluded that it was the intent of Congress was to have the statute of limitations “run against (and protect) the owner of the property at the time the cleanup occurs.” The court reasoned that if Hearthstone’s argument were accepted, “an owner could sell a recently cleaned piece of property to an innocent owner one day before the statute of limitations runs, with the result that the new owner would bear full cleanup liability under CERCLA if a recovery action was later timely filed.” Accordingly, the court saw this as contextual evidence of Congressional intent that the owner at the time of cleanup was to be considered the owner for the purpose of CERCLA liability.  In addition, relying on the date of filing of the cost recovery action contradicts the intent to have early settlements. In essence, Hearthside’s approach would require the filing of a suit in order to determine the date of ownership.  In addition, since the owner at the time of cleanup can help determine the scope of cleanup, “it follows that the same owner should be responsible for the cost of the remediation program that it had the opportunity to influence.”

DiFrancesco, Bateman, Coley, Yospin, Kunzman, Davis & Lehrer, PC (www.dbnjlaw.com ) is a full service law firm in New Jersey which provides a broad range of legal services, including the representation of clients in environmental and defense of toxic exposure matters. For additional information about the matters in this bulletin or in the firm’s environmental practice, please contactSteven A. Kunzman, Esq. who heads our Environmental and Latent Injury Litigation Department.

District Court holds the Statute of Limitations for NRD claims under CERCLA is triggered by constructive knowledge of injury by Trustee.

SteveK July 17th, 2010

On July 13, 2010, in Commissioner of the Department of Planning and Natural Resources v. Century Alumina, LLC, et.al., the Federal District Court from the St. Croix division of the Virgin Islands, held that an action to recover natural resource damages (NRD) must be commenced within 3 years of the constructive knowledge of the injury by the trustee.

The plaintiff trustee brought the claim against a number of industrial entities for the release of contaminants onto a number of industrial tracts at various times which injured the land as well as groundwater and the Caribbean Sea.  The defendants moved for summary judgment seeking dismissal of the claims under CERCLA’s limitation of actions provision, which provides that an action for NRD must be commenced within 3 years following “the date of the discovery of the loss and its connection with the release in question.” Although the statute does not state what is meant by “discovery” the court relied upon numerous prior decisions as to other statutes and other aspects of CERCLA to conclude that it is based upon the constructive knowledge of the trustee. The court went on to clarify that the knowledge of the agency, including the knowledge of any prior trustee, would be imputed to the present trustee.  Accordingly, the determination of whether there was NRD related to the discharges would require an analysis of when the trustee knew or should have known that there was an injury to the natural resource related to the discharges, which would commence the running of the time for bringing an action. With this ruling in hand, the court analyzed the facts as to each site and each defendant, dismissing some claims and allowing others to continue.

This case demonstrates that there courts will take a rational approach in considering the relationship between knowledge of a discharge of contaminants and the commencement of NRD claims. The interests of the government to pursue recovery of NRD, while important, will not allow the government to be inattentive to their statutory obligation to act promptly to seek to enforce these rights.

DiFrancesco, Bateman, Coley, Yospin, Kunzman, Davis & Lehrer, PC ( www.dbnjlaw.com ) is a full service law firm in New Jersey which provides a broad range of legal services, including the representation of clients in environmental and defense of toxic exposure matters. For additional information about the matters in this bulletin or in the firm’s environmental practice, please contactSteven A. Kunzman, Esq. who heads our Environmental and Latent Injury Litigation Department.